Which coating types are used on a vessel, and where?
| Type | Typical area | Main job |
|---|---|---|
| Epoxy anticorrosive | Underwater hull, ballast tanks, structural steel | Corrosion barrier |
| Antifouling | Underwater hull, waterline | Prevent fouling, keep hull smooth |
| Zinc-rich primer | Newbuilding shop primer, critical steel | Cathodic protection at scratches |
| Polyurethane topcoat | Superstructure, decks, topsides | UV, gloss and colour retention |
| Tank lining | Ballast, cargo, potable water | Chemical and water resistance, hygiene |
| Intumescent / fire-rated | Accommodation, engine room | Fire protection of steel |
How long should a marine coating system last?
Design life is a function of the specification, the surface preparation actually achieved and the service profile — not of the paint alone. A correctly specified and applied epoxy-plus-antifouling system is designed around the docking interval, typically three to five years for fouling control, with the anticorrosive system intended to last through several antifouling renewals.
Can I apply antifouling over an old antifouling coat?
Often yes, but only if the existing coating is sound, firmly attached and compatible. Loose or heavily leached material must be removed, and a sealer or tie-coat applied where required. Unknown old coatings are the most common cause of unexpected delamination — check compatibility before you specify.
What causes premature coating failure at sea?
The same short list appears in almost every failure investigation: inadequate surface preparation, soluble salt contamination left on the steel, coating applied below dew point or outside the temperature window, under-target dry film thickness, and exceeded overcoating intervals. None of these are paint defects.
How do I compare quotes fairly?
Compare on cost per square metre at the specified dry film thickness over the expected service life — not on price per litre. A cheaper product with lower volume solids needs more litres to reach the same thickness, and if it lasts one docking interval less, it is the more expensive option.